Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved October-2022 To December-2022
# Circle Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 ANANTHAPUR 211 0.01 8.17 1.06 100.00
2 KADAPA 146 0.01 6.65 0.44 100.00
3 KURNOOL 217 0.01 6.85 0.39 100.00
4 NELLORE 417 0.01 7.59 0.5 100.00
5 TIRUPATI 673 0.01 8.23 0.49 100.00
Total 1664 0.01 8.23 0.55 100.00