Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved July-2022 To September-2022
# Circle Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 ANANTHAPUR 394 0.0 10.35 1.02 99.49
2 KADAPA 263 0.0 9.64 0.55 100.00
3 KURNOOL 434 0.0 10.22 0.52 99.77
4 NELLORE 614 0.0 6.09 0.46 100.00
5 TIRUPATI 729 0.0 9.07 0.46 100.00
Total 2434 0.0 10.35 0.57 99.88