Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved October-2021 To December-2021
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 RENIGUNTA 30 0.22 4.12 1.15 100.00
2 TIRUPATI CCO 195 0.07 19.24 1.23 99.49
3 TIRUPATI OPERATION1 86 0.07 17.09 1.49 98.84
4 TIRUPATI OPERATION2 180 0.07 11.12 1.29 99.44
Total 491 0.07 19.24 1.29 99.39