Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved July-2021 To September-2021
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 RENIGUNTA 40 0.01 8.0 0.64 100.00
2 TIRUPATI CCO 220 0.01 15.73 1.11 97.73
3 TIRUPATI OPERATION1 110 0.01 12.57 0.51 99.09
4 TIRUPATI OPERATION2 226 0.0 16.62 0.7 99.56
Total 596 0.0 16.62 0.81 98.83