Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved October-2022 To December-2022
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 CHANDRAGIRI 13 0.01 1.11 0.34 100.00
2 PAKALA 3 0.09 0.7 0.33 100.00
3 SRIKALAHASTI OPERATION 14 0.03 4.27 1.49 100.00
4 SRIKALAHASTI RURAL 1 0.56 0.56 0.56 100.00
Total 31 0.01 4.27 0.87 100.00