Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved October-2021 To December-2021
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 CHANDRAGIRI 15 0.08 6.26 1.39 100.00
2 PAKALA 11 0.21 6.75 2.19 100.00
3 SRIKALAHASTI OPERATION 6 0.38 3.71 1.58 100.00
4 SRIKALAHASTI RURAL 4 0.45 8.51 3.31 100.00
Total 36 0.08 8.51 1.88 100.00