Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved Apr-2021 To Jun-2021
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 KALIKIRI 6 0.07 2.0 0.88 100.00
2 PILER CCO 6 0.24 3.92 0.96 100.00
3 PILER RURALS 3 4.18 12.16 7.07 66.67
Total 15 0.07 12.16 2.15 93.33