Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved July-2022 To September-2022
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 MADANAPALLI OPERATION 40 0.01 1.07 0.15 100.00
2 PUNGANUR CCO 10 0.02 6.22 1.5 100.00
3 RURAL-MADANAPALLI 6 0.02 2.15 0.49 100.00
Total 56 0.01 6.22 0.43 100.00