Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved January-2022 To March-2022
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 MADANAPALLI OPERATION 22 0.01 1.24 0.25 100.00
2 PUNGANUR CCO 4 0.63 2.99 1.87 100.00
3 RURAL-MADANAPALLI 1 0.02 0.02 0.02 100.00
Total 27 0.01 2.99 0.49 100.00