Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved July-2022 To September-2022
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 NAIDUPETA 12 0.0 0.71 0.21 100.00
2 SULLURPETA 22 0.1 3.39 0.8 100.00
3 VENKATAGIRI C AND O 4 0.06 0.81 0.34 100.00
Total 38 0.0 3.39 0.56 100.00