# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 GUDUR 25 0.11 10.68 1.82 92.00
2 GUDUR RURALS 3 0.31 17.83 6.27 66.67
3 KOTA 10 0.1 4.74 1.61 100.00
Total 38 0.1 17.83 2.12 92.11