Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved July-2021 To September-2021
# Section Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 CHILLAKUR 4 0.4 6.4 2.43 100.00
2 GUDUR RURALS-I 1 0.12 0.12 0.12 100.00
3 GUDUR TOWN-I 20 0.04 5.03 1.19 100.00
4 GUDUR TOWN-II 13 0.01 0.67 0.36 100.00
Total 38 0.01 6.4 1.01 100.00