Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved October-2022 To December-2022
# Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 ADONI 24 0.01 5.58 0.81 100.00
2 DHONE 10 0.05 6.85 1.09 100.00
3 KURNOOL 138 0.01 3.2 0.18 100.00
4 KURNOOL RURAL 17 0.02 5.72 1.09 100.00
5 NANDYAL 28 0.01 2.86 0.38 100.00
Total 217 0.01 6.85 0.39 100.00