Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved Oct-2020 To Dec-2020
# Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 ADONI 30 0.08 10.69 2.09 96.67
2 DHONE 7 0.04 1.7 0.46 100.00
3 KURNOOL 124 0.01 6.27 0.67 100.00
4 NANDYAL 20 0.02 2.94 1.13 100.00
Total 181 0.01 10.69 0.95 99.45