Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved July-2021 To September-2021
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 ALLAGADDA 9 0.0 1.11 0.58 100.00
2 KOILKUNTLA 4 0.08 2.67 0.91 100.00
3 NANDYAL 23 0.04 10.04 1.9 95.65
4 NANDYAL-CCO 7 0.07 5.07 1.21 100.00
Total 156 0.01 10.84 1.21 98.72