Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved January-2022 To March-2022
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 ATMAKURU 2 0.14 0.37 0.25 100.00
2 GUDUR 1 0.54 0.54 0.54 100.00
3 NANDIKOTKUR 5 0.0 0.55 0.22 100.00
Total 150 0.0 12.04 0.41 99.33