Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved Oct-2020 To Dec-2020
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 ATMAKURU 6 0.07 1.85 0.65 100.00
2 GUDUR 6 0.2 1.61 0.73 100.00
3 KURNOOL 63 0.01 6.27 0.66 100.00
4 KURNOOL OPERATION 9 0.03 1.99 0.84 100.00
5 KURNOOL-II 39 0.02 3.06 0.63 100.00
6 NANDIKOTKUR 1 1.0 1.0 1.0 100.00
Total 124 0.01 6.27 0.67 100.00