Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved April-2022 To June-2022
# Section Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 KALLUR 16 0.02 1.84 0.49 100.00
2 KURNOOL RURALS 15 0.16 7.03 1.88 100.00
3 ORVAKAL 7 0.01 2.76 0.62 100.00
Total 168 0.01 9.29 0.28 100.00