Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved Apr-2020 To Sep-2020
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 ATMAKURU 8 0.15 7.0 3.27 100.00
2 GUDUR 4 0.32 4.02 2.82 100.00
3 KURNOOL 139 0.12 7.0 1.63 100.00
4 KURNOOL OPERATION 28 0.14 7.0 1.49 100.00
5 KURNOOL-II 94 0.12 9.6 1.8 100.00
6 NANDIKOTKUR 9 0.16 5.55 1.34 100.00
Total 282 0.12 9.6 1.73 100.00