Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved July-2022 To September-2022
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 JAMMALAMADUGU 5 0.31 1.2 0.76 100.00
2 PRODDATUR 27 0.0 3.22 0.46 100.00
3 PRODDATUR RURALS 7 0.02 1.44 0.33 100.00
4 YERRAGUNTLA 5 0.03 1.76 1.0 100.00
Total 174 0.0 9.64 0.43 100.00