Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved January-2022 To March-2022
# Section Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 KAMALAPURAM 2 0.18 1.94 1.06 100.00
Total 16 0.01 1.43 0.56 100.00