Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved Apr-2021 To Jun-2021
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 JAMMALAMADUGU 3 0.04 1.98 0.91 100.00
2 PRODDATUR 51 0.01 4.79 0.51 100.00
3 PRODDATUR RURALS 7 0.04 6.97 1.43 100.00
4 YERRAGUNTLA 5 0.51 5.9 2.23 100.00
Total 250 0.0 12.5 0.65 99.60