Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved April-2022 To June-2022
# Section Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 CHAPADU 1 2.84 2.84 2.84 100.00
2 DUVVUR 1 0.25 0.25 0.25 100.00
3 KAJIPET 7 0.28 8.98 4.75 100.00
4 MYDUKUR 2 3.59 7.2 5.4 100.00
Total 11 0.25 8.98 4.28 100.00