Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved January-2022 To March-2022
# Section Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 KADAPA EAST 15 0.02 0.72 0.21 100.00
2 KADAPA NORTH 15 0.01 0.54 0.21 100.00
3 NGO COLONY 12 0.03 12.63 1.26 91.67
Total 42 0.01 12.63 0.51 97.62