Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved April-2022 To June-2022
# Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 ANANTHAPUR 232 0.0 12.81 0.75 99.14
2 ANANTHAPUR RURAL 72 0.03 10.64 1.51 97.22
3 GOOTY 70 0.0 12.76 0.91 98.57
4 HINDUPUR 31 0.01 5.92 0.9 100.00
5 KADIRI 19 0.0 8.33 0.92 100.00
6 KALYANDURG 19 0.0 3.45 0.83 100.00
Total 443 0.0 12.81 0.92 98.87