Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved Apr-2021 To Jun-2021
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 KALYANDURG HQ 3 0.18 0.62 0.47 100.00
2 RAYADURG 9 0.35 5.45 1.78 100.00
3 URAVAKONDA 6 0.92 4.64 1.98 100.00
Total 274 0.0 9.84 0.5 100.00