Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved Apr-2020 To Sep-2020
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 KALYANDURG HQ 13 0.25 8.25 3.06 100.00
2 KALYANDURG RURALS 9 0.15 2.56 1.03 100.00
3 RAYADURG 11 0.18 3.4 1.01 100.00
4 URAVAKONDA 10 0.12 4.01 0.92 100.00
Total 262 0.12 13.28 2.38 89.69