Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved July-2022 To September-2022
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 KADIRI TOWN 7 0.01 2.44 0.49 100.00
2 KADIRIEAST 1 0.33 0.33 0.33 100.00
3 KADIRIWEST(R) 2 0.57 0.9 0.74 100.00
4 PUTTAPARTHY 9 0.26 3.2 1.42 100.00
Total 210 0.0 10.35 0.96 99.52