Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved Jan-2021 To Mar-2021
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 KADIRI TOWN 13 0.11 2.47 1.05 100.00
2 KADIRIEAST 5 0.98 2.12 1.67 100.00
3 KADIRIWEST(R) 5 0.12 6.0 2.61 100.00
4 PUTTAPARTHY 12 0.03 5.54 1.37 100.00
Total 74 0.02 2.94 0.57 100.00