Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved April-2022 To June-2022
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 KADIRI TOWN 9 0.02 8.33 1.33 100.00
2 KADIRIEAST 1 0.77 0.77 0.77 100.00
3 KADIRIWEST(R) 2 0.48 0.74 0.61 100.00
4 PUTTAPARTHY 7 0.0 1.91 0.5 100.00
Total 232 0.0 12.81 0.75 99.14