Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved January-2022 To March-2022
# Section Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 HINDUPUR-D1 1 0.53 0.53 0.53 100.00
2 HINDUPUR-D2 1 0.03 0.03 0.03 100.00
3 HINDUPUR-RURALS 6 0.07 1.88 0.63 100.00
Total 8 0.03 1.88 0.54 100.00