Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved July-2022 To September-2022
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 ANANTAPUR-II 140 0.0 10.35 1.12 99.29
2 ANANTHAPUR 54 0.0 1.05 0.22 100.00
3 ANANTHAPUR(E) 16 0.12 7.06 2.02 100.00
Total 210 0.0 10.35 0.96 99.52