Rectification of Voltage fluctuations in APSPDCL where expansion / enhancement of network is not involved April-2022 To June-2022
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 ANANTAPUR-II 124 0.0 12.81 0.86 99.19
2 ANANTHAPUR 95 0.0 10.71 0.48 98.95
3 ANANTHAPUR(E) 13 0.09 8.61 1.75 100.00
Total 232 0.0 12.81 0.75 99.14