Rectification of Voltage fluctuations in APSPDCL where upgradation of distribution system was required Oct-2020 To Dec-2020
# Circle Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 ANANTHAPUR 4 5.71 32.66 18.4 100.00
2 KURNOOL 3 5.67 10.65 8.62 100.00
3 TIRUPATI 2 5.77 11.4 8.58 100.00
Total 9 5.67 32.66 12.96 100.00