Rectification of Voltage fluctuations in APSPDCL where upgradation of distribution system was required July-2021 To September-2021
# Circle Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 ANANTHAPUR 1 16.28 16.28 16.28 100.00
2 KADAPA 3 8.29 18.33 11.77 100.00
3 TIRUPATI 3 16.01 33.3 22.48 100.00
Total 7 8.29 33.3 17.01 100.00