Rectification of Voltage fluctuations in APSPDCL where upgradation of distribution system was required April-2022 To June-2022
# Circle Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 ANANTHAPUR 23 13.77 63.09 25.96 100.00
2 KADAPA 30 14.69 78.98 33.63 100.00
3 KURNOOL 38 13.51 65.84 30.72 100.00
4 NELLORE 42 13.34 56.81 24.1 100.00
5 TIRUPATI 33 13.37 83.29 28.13 100.00
Total 166 13.34 83.29 28.4 100.00