Rectification of Voltage fluctuations in APSPDCL where upgradation of distribution system was required July-2021 To September-2021
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 TIRUPATI CCO 2 16.01 33.3 24.65 100.00
Total 2 16.01 33.3 24.65 100.00