Rectification of Voltage fluctuations in APSPDCL where upgradation of distribution system was required April-2022 To June-2022
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 PAKALA 1 28.69 28.69 28.69 100.00
2 SRIKALAHASTI OPERATION 3 16.17 35.17 23.05 100.00
Total 4 16.17 35.17 24.46 100.00