Rectification of Voltage fluctuations in APSPDCL where upgradation of distribution system was required April-2022 To June-2022
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 KURNOOL 8 13.51 37.11 19.13 100.00
2 KURNOOL OPERATION 3 15.79 39.69 24.94 100.00
3 KURNOOL-II 4 14.35 19.44 17.34 100.00
Total 15 13.51 39.69 19.81 100.00