Rectification of Voltage fluctuations in APSPDCL where upgradation of distribution system was required April-2022 To June-2022
# Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 KADAPA 5 18.51 69.96 38.88 100.00
2 PRODDATUR 11 14.69 78.98 32.72 100.00
3 PULIVENDULA 1 54.95 54.95 54.95 100.00
4 RAJAMPET 11 14.8 70.01 31.07 100.00
5 RAYACHOTY 2 18.0 39.8 28.9 100.00
Total 30 14.69 78.98 33.63 100.00