Rectification of Voltage fluctuations in APSPDCL where upgradation of distribution system was required April-2022 To June-2022
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 RAYACHOTY 1 18.0 18.0 18.0 100.00
2 RAYACHOTY RURALS 1 39.8 39.8 39.8 100.00
Total 5 18.51 69.96 38.88 100.00