Rectification of Voltage fluctuations in APSPDCL where upgradation of distribution system was required April-2022 To June-2022
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 KODUR 1 22.46 22.46 22.46 100.00
2 RAJAMPET 6 14.8 55.94 28.41 100.00
3 VONTIMITTA 4 16.83 70.01 37.22 100.00
Total 5 18.51 69.96 38.88 100.00