Rectification of Voltage fluctuations in APSPDCL where upgradation of distribution system was required April-2022 To June-2022
# Sub-Division Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 PULIVENDULA 1 54.95 54.95 54.95 100.00