Rectification of Voltage fluctuations in APSPDCL where upgradation of distribution system was required Oct-2020 To Dec-2020
# Section Number of Complaints Min Duration(Days) Max Duration(Days) Average Duration(Days) Complaints Resolved(%)
1 HINDUPUR-D1 1 5.71 5.71 5.71 100.00
Total 1 5.71 5.71 5.71 100.00