Title Transfers effected in APSPDCL April-2022 To June-2022
# Section Number of Requests TT Min Duration(Days)TT Max Duration(Days)TT Average Duration(Days)TT Requests Handled(%) TT
1 MUTHUKURU 9 1.07 6.18 3.49 100.00
2 NELLORE RURAL-1 35 0.75 7.83 3.43 97.14
3 NELLORE RURAL-2 115 0.0 11.02 2.26 94.78
4 NELLORE RURAL-3 79 0.0 9.64 2.36 96.20
5 VENKATACHALAM C-O 12 0.0 6.22 1.79 100.00
Total 250 0.0 11.02 2.48 96.00