Title Transfers effected in APSPDCL July-2021 To September-2021
# Sub-Division Number of Requests TT Min Duration(Days)TT Max Duration(Days)TT Average Duration(Days)TT Requests Handled(%) TT
1 JAMMALAMADUGU 61 2.34 4.56 3.29 100.00
2 PRODDATUR 225 0.39 13.87 3.59 89.33
3 PRODDATUR RURALS 29 0.52 4.77 2.1 100.00
4 YERRAGUNTLA 6 1.02 3.03 1.8 100.00
Total 193 0.36 36.77 6.13 78.76