Conversions from LT Single phase to 3 phase done in APSPDCL July-2021 To September-2021
# Circle Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 ANANTHAPUR 11 0.03 20.01 5.76 100.00
2 KADAPA 20 1.38 31.05 8.51 95.00
3 KURNOOL 23 1.64 39.53 8.69 95.65
4 NELLORE 44 0.64 84.35 11.15 90.91
5 TIRUPATI 65 0.37 68.26 22.25 69.23
Total 163 0.03 84.35 14.54 84.05