Conversions from LT Single phase to 3 phase done in APSPDCL January-2022 To March-2022
# Division Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 CHITTOOR TOWN 1 14.25 14.25 14.25 100.00
2 MADANAPALE 1 20.75 20.75 20.75 100.00
3 TIRUPATI RURALS 3 24.25 29.25 27.18 100.00
4 TIRUPATI TOWN 19 0.62 42.75 16.08 89.47
Total 24 0.62 42.75 17.59 91.67