Conversions from LT Single phase to 3 phase done in APSPDCL Jan-2021 To Mar-2021
# Division Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 CHITTOOR TOWN 2 4.59 31.25 17.92 50.00
2 MADANAPALE 1 16.33 16.33 16.33 100.00
3 PUTTUR 1 16.0 16.0 16.0 100.00
4 TIRUPATI TOWN 2 14.26 15.56 14.91 100.00
Total 6 4.59 31.25 16.33 83.33