Conversions from LT Single phase to 3 phase done in APSPDCL April-2022 To June-2022
# Division Number of Requests PH Min Duration(Days)PH Max Duration(Days)PH Average Duration(Days)PH Requests Handled(%) PH
1 CHITTOOR RURALS 1 19.47 19.47 19.47 100.00
2 CHITTOOR TOWN 9 1.88 28.31 19.12 100.00
3 MADANAPALLE 6 10.54 22.69 17.78 100.00
4 PILERU 1 2.84 2.84 2.84 100.00
5 PUTTUR 4 5.85 20.37 14.83 100.00
6 TIRUPATI RURAL 6 4.86 33.85 15.74 83.33
7 TIRUPATI TOWN 53 0.65 32.13 12.26 98.11
Total 80 0.65 33.85 13.81 97.50